Tariff cost on ATC plan
$100M
FAA Administrator Bryan Bedford, House subcommittee hearing, Sept. 15, 2026; largely attributed to imported radar systems
Phase 1 cost vs. appropriation
$16B vs. $12.5B
Bedford testimony, Sept. 15, 2026; Congress approved the $12.5B in July 2025
Phase 2 funding request
$10B+
Bedford testimony, Sept. 15, 2026; FAA seeking additional congressional authorization
Telecom upgrade cost escalation
$4.75B → $5.91B
GAO-26-107992, released Sept. 14, 2026
The event
A $100M tariff lands on a $12.5B federal capex line
On Sept. 15, 2026, FAA Administrator Bryan Bedford testified before a House subcommittee that phase one of the Brand New Air Traffic Control System (BNATCS) would cost $16 billion — $3.5 billion more than the $12.5 billion Congress appropriated in July 2025 through the One Big Beautiful Bill Act. Two days later, Reuters reported Bedford had disclosed an additional ~$100 million tariff cost on the program, and that the hit is concentrated on radar systems being purchased from suppliers with non-U.S. production footprints.
The math
Phase 1 needs $3.5B more, and GAO says the agency has under-counted operating costs
Bedford said the FAA is funding the gap out of its facilities and equipment budget. The Government Accountability Office, in a report dated Sept. 14, 2026 (GAO-26-107992), said the agency has not produced a reliable lifecycle cost estimate and has not built an integrated master schedule — the program is split into 11,389 separate project schedules. The GAO also flagged that the telecommunications upgrade, originally priced at $4.75 billion, has risen to $5.91 billion, and that FAA has not budgeted for most operating costs over the life of phase one.
| Item | Authorized / Estimated | Source |
|---|---|---|
| Total BNATCS appropriation (July 2025) | $12.5B | One Big Beautiful Bill Act, FAA fact sheet |
| — of which ATC modernization | $9.0B | FAA, May 8, 2025 announcement |
| — of which facilities construction | $3.5B | FAA, May 8, 2025 announcement |
| Phase 1 actual cost (Bedford testimony) | $16B | Reuters, Sept. 15, 2026 |
| Phase 1 funding gap | ~$3.5B | Bedford testimony |
| Tariff cost on radar purchases | ~$100M | Reuters / Yahoo Finance, Sept. 17, 2026 |
| Phase 2 request (next tranche) | $10B+ | Bedford testimony |
| Telecom upgrade original estimate | $4.75B | GAO-26-107992 |
| Telecom upgrade revised estimate | $5.91B | GAO-26-107992 |
The supply chain
The radar contracts are already routing around the tariff wall
The $100M tariff exposure is concentrated on radar procurements, and the two awardees of the January 2026 Radar System Replacement contracts are actively moving production to U.S. soil. RTX's Collins Aerospace won a $438 million contract to install its Condor Mk3 cooperative surveillance radar; the company has committed $26.5 million to its Largo, Florida facility for the work. Indra Sistemas won a $342 million contract for next-generation surveillance radars and is building them at a new manufacturing Center of Excellence in Overland Park, Kansas, backed by a $50 million capital commitment and a separate $7.5 million, 25,000 sq ft Olathe radar plant — together creating more than 340 U.S. jobs.
FAA Radar System Replacement contract awards, January 2026
Total $780M covers up to 612 ground-based radars by June 2028
Unit: $ millions
RTX (Collins Aerospace)
$M; cooperative & non-cooperative radars; Condor Mk3
438
Indra Sistemas
$M; next-gen surveillance radars; Kansas production
342
Both contracts are designed to retire legacy radars — many dating to the 1980s — by June 2028. Domestic production neutralizes the tariff pass-through and puts both firms on the right side of an emerging Buy-American preference inside the program.
The contractor map
\"America First\" redraws who gets the next contract
The Air Current reported that U.S. prime contractors — L3Harris, RTX and Leidos — have spent nearly two years lobbying for reciprocal restrictions that would lock European-owned Thales, Indra and Austria's Frequentis out of BNATCS contracts, citing a 2024 EU regulation that bars non-EU ATC suppliers. Indra has pre-empted that risk by localizing production; Thales has not, and Frequentis is positioned only on the Voice-over-IP Communications Enterprise (VoICE) program so far.
- L3Harris — won the July 2026 FAA Airspace Surveillance contract covering the national aircraft tracking network through 2045 and is past 50% on the FAA Telecommunications Infrastructure backbone, due complete in 2027
- RTX — secured the $438M Collins radar contract Jan. 5, 2026 and is now reportedly bidding for a larger role in the $12.5B integration program
- Leidos — incumbent on the FAA's ERAM, ATOP, TBFM, TFDM and Future Flight Services systems; $292M recent award and $7.6M modification logged Aug. 14, 2026
- Indra Sistemas — $342M FAA radar contract plus $57.5M combined U.S. facility investment; the rare foreign-owned prime with onshore production
- Thales — has signaled readiness to support ATC modernization, but no major BNATCS contract awarded; ownership nationality is now an explicit contract risk
- Peraton (private) — $1.5B, 10-year BNATCS prime integrator contract awarded Dec. 4, 2025; Politico reported in August 2026 the FAA is frustrated and weighing scope reductions
The constraint
Tariffs are a symptom — the bottleneck is integration and timing
The $100M tariff is small next to the structural issues. Peraton — picked as sole prime integrator in December 2025 on a $1.5 billion, 10-year contract — is reportedly under pressure eight months in, with Politico reporting in August 2026 that the FAA is considering scope reductions. With a fragmented master schedule, no reliable operating-cost forecast, and a phase-two authorization still pending, the working-capital squeeze on the F&E line will determine whether radar and telecom deployments hit their 2028 milestones or slip into the next authorization cycle.
The read for investors
Domestic primes and the Spanish outsider are the cleanest plays
Tariffs reward suppliers with U.S. production and penalize those without. L3Harris has the longest-dated exposure — its surveillance contract runs through 2045 — and the highest-confidence domestic build-out (FTI on track for 2027, ~200 telecom engineers in Melbourne, FL). RTX has the largest near-term contract win ($438M radar) and is publicly bidding for an expanded BNATCS role. Leidos sits on the most mission-critical FAA software (ERAM en route automation), giving it the stickiest incumbency even if its dollar exposure to the $12.5B program is smaller. Indra is the contrarian play — foreign-owned, but already onshore in Kansas and awarded a $342M radar contract that routes around the tariff wall.
| Company | ATC role | Key U.S. contract | Listed venue |
|---|---|---|---|
| L3Harris | Surveillance + telecom backbone | FAA contract through 2045 (surveillance); FTI 50%+ complete (2027 target) | NYSE: LHX |
| RTX / Collins Aerospace | Cooperative & non-cooperative radars | $438M Radar System Replacement (Jan. 2026) | NYSE: RTX |
| Leidos | ATC software (ERAM, TFDM, FFSP) | ERAM/STARS follow-on ceiling $6.77B; $292M recent award | NYSE: LDOS |
| Indra Sistemas | Surveillance radars (foreign-owned, U.S.-produced) | $342M FAA contract; $57.5M Kansas investment | BME Madrid: IDR.MC |
| Thales | Positioned for ATC modernization (no BNATCS contract awarded) | Foreign-ownership headwind under \"America First\" | Euronext Paris: HO.PA |
How the listed suppliers map to the $100M tariff and the $16B bill
- Surveillance contract runs through 2045, locking in long-tail revenue tied to the BNATCS phase-1 deployment window through 2028
- FTI backbone past 50% complete and on track for 2027 — removes the largest execution risk from the FAA's $5.91B telecom line
- $100M tariff on radar hits competitors more; L3Harris builds the bulk of its ATC gear domestically in Melbourne, FL
- $438M Collins Aerospace radar award (Jan. 2026) is the single largest ATC contract in scope, with U.S. production at the Largo, FL plant —fully shields RTX from the $100M radar tariff
- RTX is publicly bidding for a larger role in the $12.5B integration program beyond the current Phillips scope
- Collins's Condor Mk3 cooperative radar is the workhorse for the 612-radar replacement by June 2028
- Incumbent on the FAA's ERAM, ATOP, TBFM, TFDM and Future Flight Services — stickiest ATC software franchise but small dollar share of the $12.5B program
- Phase 1 cost overruns and the Peraton integrator friction could pull more integration work into Leidos's orbit
- GAO finding of no integrated master schedule across 11,389 projects raises the value of the systems integrator that already runs ERAM
- $342M FAA radar contract (Jan. 2026) plus $50M Overland Park and $7.5M Olathe investments route around the $100M tariff entirely
- Rare foreign-owned prime with onshore production — converts the 'America First' headwind into a relative advantage over Indlessey-controlled European entities
- Madrid listing exposes global investors to U.S. ATC capex without buying a U.S. defense multiple
- No major BNATCS contract awarded despite public readiness statements, and the foreign-ownership row is now a formal lobbying issue for U.S. primes
- The $100M radar tariff and Buy-American tilt narrow the addressable scope of any future BNATCS award to U.S.-produced systems
- Watch the next BNATCS integration task orders under the Peraton IDIQ — Thales participation would mark a reversal; exclusion would confirm the bear case