Force majeure issued
Sept 24, 2026
Notice from Oracle to Stack Infrastructure (Blue Owl unit) on Project Jupiter
Project size
$165B
1,400-acre, 2.45 GW AI campus in Doña Ana County, NM
Project-finance debt
$18B
Leveraged loan from ~20 banks; trading at 89–91¢ on the dollar
Blue Owl equity at risk
~$3B
Stack earns ~9% annualized during construction
Pipeline delay
~6 months
Green Chile pipeline in-service pushed from Aug 15, 2026 to Feb 1, 2027
Oracle RPO
$664B
Q1 FY27, up $209B YoY; ~$30B in new AI cloud contracts added
On September 24, 2026, Oracle sent a force-majeure notice to Stack Infrastructure — a unit of Blue Owl Capital — covering Project Jupiter, the $165 billion, 2.45-gigawatt Stargate AI data center it is leasing in Doña Ana County, New Mexico. The notice does not exit the tenancy; it preserves the right to delay lease payments if the campus misses its 2028 go-live target. Within hours, Oracle shares fell about 3–4% and project-finance debt tied to the campus — $18 billion of leveraged loans arranged by Santander and Jefferies — was already trading at 89–91 cents on the dollar, a roughly 11-point haircut that put lenders, not the equity sponsor, on the hook for the delay.
The unusual shape of this force majeure
Force-majeure clauses are usually invoked by a builder or supplier when an external event — war, natural disaster, regulatory denial — prevents performance. What makes Project Jupiter novel is that the tenant is invoking it. Oracle is not the party unable to deliver; it is the party that may stop paying if the landlord misses a hand-over date. Bloomberg first reported the move, citing people familiar with the notice, and an Oracle spokesperson told reporters that \"force-majeure notices are commonplace in developments of this scale and are often used to preserve contractual rights among project partners.\" That framing is accurate on the contract — but it conceals the directional shift: the tenant is now laying the groundwork to offload a one-year delay risk onto the project’s equity sponsor and its bank lenders.
How $18 billion of project debt got priced at 89¢
Project-finance loans for AI campuses look like real-estate paper but trade like credit. The $18 billion Jupiter facility — underwritten by roughly 20 institutions led by Santander and Jefferies, and signed in November 2025 — was meant to be syndicated out to a wider investor base. According to the Financial Times and follow-on reporting, that distribution has stalled: lead banks are sitting on a larger share of the loans than originally planned, and the secondary quotes slipped to 89–91 cents on the dollar in mid-September. A nine-to-eleven cent discount on a recently-issued leveraged loan is a market statement — investors want a cushion against construction delay, local opposition, and the credit quality of a project whose anchor tenant has just signaled it may withhold rent.
| Item | Detail | Source |
|---|---|---|
| Project-finance loan | $18B from ~20 banks | Bloomberg, Nov 7, 2025 |
| Lead arrangers | Santander, Jefferies | FT, Sept 18, 2026 |
| Secondary bid (mid-Sept) | 89–91¢ on the dollar | FT, Sept 18, 2026 |
| Blue Owl equity in project | ~$3B | Reuters, Sept 24, 2026 |
| Stack construction return | ~9% annualized | WSJ, Sept 2026 |
| First-phase schedule slip | ~7 months vs. original Nov 2026 target | The Dark Side of the Boom, Sept 2026 |
| Pipeline in-service | Feb 1, 2027 (from Aug 15, 2026) | Construction Review, Sept 22, 2026 |
Project Jupiter build progress is bottlenecked by power, not concrete
Share of physical scope completed as of Sept 22, 2026; pipeline date revised to Feb 1, 2027
Unit: % complete
Campus site (overall)
Up from 17% in July
26
Fuel-cell microgrid
Critical path for first compute delivery
10
The supply chain that suddenly has timing risk
A force-majeure notice on a megaproject does not just move paper between Oracle and Blue Owl — it changes the order cadence for every supplier with a delivery slot in 2027 or 2028. The most exposed equipment counterparty is Bloom Energy, which signed on in April 2026 to power the campus with natural-gas fuel cells. The pipeline denial hits Bloom Energy’s order book at exactly the moment the company has rerated on the AI-data-center thesis; the stock is up roughly 230% over the past year even as the original gas-pipeline design is now uncertain. Chip vendors are next in line: Oracle’s announced plan to deploy 50,000 AMD MI450 accelerators in calendar Q3 2026 and the larger NVIDIA push for OpenAI workloads both depend on the New Mexico campus coming up on schedule. Micron — exposed through HBM attached to both — is a third-order play that moves on the order book rather than the project itself.
- Bloom Energy — sole named on-site power vendor; order pacing now depends on whether the gas pipeline can be rerouted and whether Oracle pivots to grid or hybrid microgrid. The stock’s230% one-year rally makes any delay news high-volatility.
- Energy Transfer — builder of the Green Chile 17-mile pipeline extension to deliver up to 400M cubic feet/day to Jupiter. State-land denials in March and July 2026 have already pushed in-service from Aug 15, 2026 to Feb 1, 2027, reducing near-term tariff revenue on the project.
- NVIDIA — Jupiter is part of the Stargate buildout that uses NVIDIA GB200/Vera Rubin racks; the company’s data-center revenue was $89.0B in Q2 FY27 (filed Aug 26, 2026), so any single-site slip is small relative to total demand but large as a sentiment signal.
- AMD — Oracle’s 50,000 MI450 cluster was already slated for Q3 2026; if Jupiter slips, AMD’s diversification narrative for non-NVIDIA AI silicon takes a small hit on timing.
- Micron — HBM3E/HBM4 demand correlates with shipped AI accelerators; a one-year project delay pushes the memory attach out rather than cancels it, but shifts quarterly mix.
Oracle’s RPO is up $209 billion — so why invoke now?
Oracle reported $664 billion of remaining performance obligations at the end of Q1 FY27 (Aug 31, 2026), up $209 billion year-on-year, with about half expected to convert to revenue inside36 months. Cloud revenue grew 33%, and Oracle Cloud Infrastructure (OCI) grew 121% — both numbers that make a force-majeure notice look odd if you only watch the headline backlog. The numbers only line up if you watch the free-cash-flow column too: capex ran at 105% of trailing operating cash flow, Oracle burned $23.7B of free cash last fiscal year, and Q1 FY27 interest expense was $1.43 billion — up 55% year-on-year. A delayed lease means a delayed cash drain, and [Oracle](orcl]’s bondholders and equity holders both benefit from the optionality the clause preserves. The notice is a treasury move as much as a legal one: it gives the company a contractual escape valve against $1.5 trillion of cumulative AI infrastructure financing that, per Reuters’ sources, is required by 2028.
Oracle revenue is scaling fast while free cash flow stays deeply negative
Quarterly revenue and Q1 FY27 free cash flow burn; fiscal year ends May
Unit: USD millions
Q1 FY26 revenue
14,926
Q2 FY26 revenue
16,058
Q3 FY26 revenue
17,190
Q4 FY26 revenue
19,184
Q1 FY27 revenue
19,345
Two precedents in nine months: Michigan and Abilene
- Michigan — In December 2025, Blue Owl walked away from a planned $10 billion financing commitment for a 1 GW Oracle-anchored campus in Saline Township after talks stalled. Oracle said talks were on schedule and did not include Blue Owl; the stock fell roughly 5% on the news. The Michigan project is the cleanest prior example of AI-build equity pulling out before force-majeure language is invoked.
- Abilene (TX) — In March 2026, Oracle and OpenAI scrapped plans to expand the flagship Stargate campus by 600 MW after financing negotiations with Crusoe broke down. Meta is reported to be weighing a lease on the abandoned expansion. The pattern across all three events: equity and bank financing arrives later than the press-release ambition, and the tenant-developer pair renegotiates scope rather than walking away from the campus.
Horizons: what moves in days–quarters vs. one to three years
Short-term (days to quarters): the binding catalysts are court and regulator decisions, not data-center demand. The New Mexico Supreme Court unanimously rejected opposition petitions on Sept 17, 2026 and lifted stays on the air-quality and water permits, which lets the State Environment Department resume hearings and lets Oracle resume Santa Teresa well pumping. Expect the next60–90 days to bring either a path forward on a rerouted pipeline route or an explicit Oracle pivot to a grid-plus-fuel-cell hybrid. The market is already pricing the noise: Oracle shares dropped about 4% on Sept 24, NVIDIA, AMD and Micron slipped on follow-through, and [Blue Owl](owl]’s stock — already down 46% on the year — has the most direct downside if the loan syndicate has to take writedowns.
Long-term (one to three years): the structural lesson is that AI infrastructure is being absorbed into ordinary project-finance discipline. The 11¢ secondary-market haircut on $18B of paper is the first hard market signal that lenders are repricing gigawatt-scale AI campuses against construction and political risk, not against cloud-customer credit. Sites with already-permitted grid interconnection or behind-the-meter generation (solar, nuclear PPAs, fuel cells on existing gas rights) will trade at a premium; sites requiring new state-land easements or new pipeline routes will price in 12–18 month delays from day one. Bloom Energy, NVIDIA and AMD all retain demand at the chip and equipment level, but the order timing for new campuses now bends to permit and lender calendars, not to data-center operator roadmaps.
Synthesis: a turning point for AI build economics
The force-majeure notice on Project Jupiter is best read as a marker that the AI-infrastructure cycle has crossed from \"build and bill\" into \"build, bill, and reprice.\" [Oracle](orcl]’s $664 billion RPO is real and growing, but the cash needed to convert it sits behind permits, pipelines, and a $1.5 trillion external financing gap by 2028 — three bottlenecks that any single sponsor cannot unilaterally absorb. The clean read for investors: monitor the bid–ask on AI-campus project loans and the cadence of new state-land rulings as the leading indicators, not hyperscaler revenue headlines.
Investable names
- Tenant-issued force majeure preserves cash-flow optionality against $1.5T in external financing needed by 2028, supporting balance-sheet flexibility while protecting the $664B RPO from impairment.
- Quarterly free cash flow remains negative $23.7B TTM and Q1 FY27 capex ran at 123% of operating cash flow, so a one-year lease delay cuts FY28–FY29 cash drag by tens of billions.
- Counter-risk: the same notice invites lender scrutiny across the Stargate campus portfolio and mayraise the project-finance cost-of-capital for every subsequent Oracle campus by 50–150 bps.
- ~9% construction return on $3B of equity in Project Jupiter now turns into negative carry once a one-year delay hits, compounding a stock already down 46% over the past year.
- Bank consortium exposure — Santander and Jefferies leading $18B with distribution stalled — raises the probability of follow-on capital calls or writedowns if Jupiter slips beyond 2028.
- Watch: a successful pipeline reroute would restore the original 9% build return and the equity cushion; a pivot to grid power makes the project cheaper but compresses Stack’s role over time.
- Sole named on-site power vendor for the 2.45 GW campus; the fuel-cell order book loses one full year of deployment if the pipeline stalls beyond Feb 2027, even as 230% one-year stock performance has already priced most of the AI-data-center thesis.
- A forced pivot to a hybrid microgrid (gas where permitted + grid + storage) preserves unit volume but at lower price per kilowatt, compressing project margin.
- Counter: the regulatory risk validates Bloom Energy’s broader data-center pipeline with hyperscalers already on grid; long-run TAM widens even if the New Mexico site slips.
- Data-center revenue of $89.0B in Q2 FY27 (filed Aug 26, 2026) is large enough that a single 2.45 GW campus slip moves quarterly mix by tenths of a percent, not whole percentages.
- Watch item: if Oracle defers Jupiter from 2028 to 2029, ~10–15K GB200/Rubin rack-equivalents shift out of FY27 and into FY28 capex, modestly tightening Q3 FY27 supply-demand on rack margins.
- Sustained loan bid below 92¢ at Jupiter would cool sentiment around the broader Stargate capex narrative, the larger risk for the name.
- Oracle’s commitment to deploy 50,000 AMD MI450 accelerators starting Q3 2026is on-track for existing sites, but Jupiter slip pushes a portion of that order into FY28, shifting the diversification narrative rather than breaking it.
- Q2 2026 data-center revenue of $5.8B makes AMD a second-order derivative of any Stargate slip; sentiment effect outweighs near-term P&L effect.
- Counter: any Oracle pivot away from NVIDIA-only designs toward more AMD silicon converts Jupiter’s delay into long-run share gain for AMD.
- HBM attach to NVIDIA and AMD accelerators means a Jupiter slip delays, not cancels, the HBM3E/HBM4 unit shipments tied to Jupiter-bound racks.
- Fundamentals: memory pricing cycles run on hyperscaler CapEx, which is still up sharply YoY; a single2.45 GW delay is unlikely to move FY27 HBM revenue by more than 1–2%.
- Watch: a multi-site cascade across Stargate would compress the FY28 HBM ramp materially and is the asymmetric risk for Micron here.
- Builder of the 17-mile Green Chile pipeline extension that would deliver up to 400M cubic feet/day to Project Jupiter; two state-land permit rejections have already moved in-service from Aug 15, 2026 to Feb 1, 2027.
- On a one-year delay, tens of millions of dollars in expected tariff revenue defers and competes for capital with Energy Transfer’s broader project backlog.
- Counter: a successful reroute with BLM approval on federal land restores the original tariff schedule and validates ET’s siting model.
- Stated Stargate partner alongside Oracle and OpenAI for the 10 GW, $500B U.S. build; a Project Jupiter slip calls into question the timing cadence of adjacent Stargate campuses, on which SoftBank’s equity contribution depends.
- Indirect balance-sheet exposure: SoftBank’s $30B/year OpenAI-Oracle revenue estimate ties to Jupiter-class campuses coming online on schedule, making each delay a hit to the assumed conversion curve.
- Watch: SoftBank’s Q3 FY26 (ending Dec 2026) results disclosure on Stargate commitmentswill be the first read on whether the Jupiter slip is being absorbed in guidance.