$3.3B USDA Loan to a Georgia Co-op Just Wired Rural America Into the AI Power Grid insight cover
Industry NewsGEV · PWR · VST•15 min read

$3.3B USDA Loan to a Georgia Co-op Just Wired Rural America Into the AI Power Grid

USDA's record $3.3 billion Rural Utilities Service loan to Oglethorpe Power — a nonprofit serving 38 Georgia electric co-ops — is the first federal rural-utility financing formally tied to data-center load growth. With Google's 948-acre Monroe County site adjacent to the new 1,425 MW Smarr plant and GE Vernova sitting on a $176B backlog, the deal pulls the rural co-op stack off the agricultural sidelines and into the AI buildout — and puts Vistra, Constellation Energy, and Quanta Services on collision course with Southern Company for the next dollar of load growth.

Published Oct 17, 2026Updated Oct 17, 2026

Loan amount

$3.3B

Largest in RUS history; closed Oct 14, 2026

All-in rate

~6.3%

Treasury + 1/8 percentage point; 30-year amortization

Project capacity

1,425 MW

Two-unit GE Vernova 7HA.03 combined cycle

RUS demand pipeline

$8.6B

Under Secretary Glen Smith told Reuters; ~$7B authorized for FY2026

The Deal

USDA Just Made Its Largest RUS Loan Ever — for a Plant It Says Isn't for Data Centers

On October 14, 2026, USDA Secretary Brooke Rollins stood at the construction site of Oglethorpe Power's Smarr Combined-Cycle plant in Monroe County, Georgia, and signed off on a $3.3 billion loan — the largest single award in the 90-year history of the agency's Rural Utilities Service. The two-unit, 1,425 MW natural-gas facility is being built for a nonprofit cooperative that wholesales electricity to 38 member-owned electric membership corporations (EMCs) across rural Georgia, with commercial operation slated for 2029.

Loan amount

$3.3B

Largest in RUS history; closed Oct 14, 2026

All-in rate

~6.3%

Treasury + 1/8 percentage point; 30-year amortization

Project capacity

1,425 MW

Two-unit GE Vernova 7HA.03 combined cycle

RUS demand pipeline

$8.6B

Under Secretary Glen Smith told Reuters; ~$7B authorized for FY2026

Member co-ops served

38

Oglethorpe Power wholesale customers in Georgia

Annual member savings

~$25M/yr

Oglethorpe CEO estimate vs. prior Treasury-rate debt

The interesting wrinkle: the plant was not built to serve a data center, Oglethorpe spokesperson Blair Romero told Reuters. USDA Under Secretary Glen Smith nonetheless called out Georgia's data-center growth — including Alphabet's 948-acre Monroe County land buy — as exactly the kind of load RUS is being rewired to absorb. Both sides of that quote are load-bearing for the trade.

Demand Anchor

Monroe County Has Become the Most-Watched Load Pocket in the Southeast

The Smarr plant sits in the same Monroe County as Plant Scherer — Georgia Power's 3,520 MW coal-fired complex that the Georgia Public Service Commission voted in July 2025 to keep running past its 2028 retirement date specifically to serve data-center demand. One county over, in Fayetteville, Microsoft's Fairwater Atlanta AI data center is already in commercial operation on a 615-acre QTS-owned campus; in October 2025, Microsoft unveiled Fairwater as the second node of an AI \"superfactory\" connected to Wisconsin in near-real-time.

  • Alphabet paid ~$42M (per county records) for 948 acres off I-75 in Monroe County in October 2025 for a data center; in September 2026 the county approved a plan splitting a projected $1.2B in tax and construction revenue over 20 years
  • Microsoft's Fairwater Atlanta (Fayette County) is online, with multiple buildings in flight and Microsoft confirming a closed-loop cooling design that uses \"almost zero water\" — a direct response to local ratepayer and water concerns
  • Georgia Power's approved 2025 IRP allocates roughly 9,885 MW of new generation through 2031 to meet projected demand, with fossil fuels — including extended coal operation — driving most of the additions; the plan could cost customers an estimated $50–60B over its life
  • 26 data centers are under construction within 60 miles of Atlanta (as of October 2025), and Georgia now ranks #1 nationally for data-center expansion, with roughly 48 facilities and about 6,970 MW of pipeline capacity tracked across 24 operators
The Smarr loan is sized for 800,000 homes of capacity — but the county's actual growth driver is a handful of hyperscale campuses. That mismatch is exactly where the investable trade sits: the rural stack underwrites the backbone, the hyperscalers consume it, and a private cooperative sits in the middle holding both ends.

Upstream Supply Chain

Turbines, Steel, and the 7.8-Mile Wire — Where the $3.3B Actually Lands

Every dollar of RUS financing on a generation project flows downstream into a small set of US-listed suppliers. The Smarr plant is a textbook example: GE Vernova is supplying the two 7HA.03 gas turbines (manufactured in Greenville, South Carolina); Kiewit subsidiary The Industrial Company is the EPC contractor; the project also includes a 7.8-mile, 500-kV transmission line connecting the plant to the regional grid — exactly the kind of high-voltage work Quanta Services dominates.

Where the Smarr CC budget lands — direct counterparty beneficiaries
WorkstreamCounterpartyStatusSource
Gas turbines (2 units)GE Vernova (GEV)7HA.03 selected May 2025Oglethorpe Power press release
EPC contractorKiewit / The Industrial Co. (private)Awarded Jan 2026; ~$2.5B EPC valueENR, Jan 30, 2026
500-kV transmission line (7.8 mi)TBD; Quanta-type scopeConstruction late 2027Oglethorpe, ENR
Step-down transformers/switchgearTBD; constrained market44-week avg. lead time industry-wideGiga Energy lead-time survey, Aug 2026
Wholesale off-take38 Georgia EMCs (private)Oglethorpe member systemOglethorpe corporate site

The turbine selection is the most consequential decision in the deal. GE Vernova's 7HA.03 is the same heavy-duty frame Microsoft just bought seven of for a Texas data center, and the same family Alphabet/xAI's Colossus 1 is running on. GE Vernova ended Q2 2026 with a $176 billion total backlog and reported data-center orders above $5 billion in the first half alone — more than double its full-year 2025 total. The company has guided 2026 revenue up to $45.5–46.5 billion and free cash flow to $11.5B+, with CEO Scott Strazik pointing to 2031 reservation slots already being taken.

GEV total backlog

$176B

Q2 2026, reported Jul 22, 2026

GEV data-center orders (H1)

>$5B

More than double FY2025 full-year total

GEV Q2 revenue

$11.1B

Q2 FY2026, filed Jul 22, 2026

GEV 2026 revenue guide

$45.5–46.5B

Raised with Q2 results (was $44.5–45.5B)

Cross-Industry Impact

Rural Gas vs. Hyperscale Nuclear — Two Doors, One Load

The Smarr deal is one of two models competing for the same megawatt of AI load. The other is long-dated, hyperscale-direct nuclear power purchase agreements — and that side has already booked the marquee names. Constellation Energy holds a 20-year PPA with Microsoft to restart Three Mile Island Unit 1 as the 835 MW \"Crane Clean Energy Center,\" targeted for 2028 operation; another 20-year PPA with Meta Platforms for ~1,121 MW from the Clinton Clean Energy Center in Illinois; and a 20-year PPA with Alphabet to support ~890 MW of capacity across 11 reactors.

Long-term AI power deals — the nuclear PPA stack as of Q4 2026
Counterparty (buyer / seller)CapacityTermSource
Microsoft / Constellation (CEG)835 MW (Three Mile Island restart)20-yearConstellation press release, Sep 20, 2024
Meta / Constellation (CEG)~1,121 MW (Clinton Clean Energy Center)20-yearUtility Dive, Jun 6, 2025
Google / Constellation (CEG)~890 MW (11 reactors, uprates)20-yearAmerican Nuclear Society
Meta / Vistra (VST)>2,600 MW (Perry, Davis-Besse, Clinton)20-yearVistra 8-K, Jan 9, 2026
Amazon / Constellation (CEG)190 MW addition20-yearConstellation, Sep 30, 2026
Alphabet / Oglethorpe (no PPA yet)~948 acres in Monroe Countyn/aCounty property records, Oct 2025

Vistra's January 2026 Meta package was the inflection: more than 2,600 MW from three PJM nuclear plants (Perry, Davis-Besse, and Clinton), with uprate work to begin delivering additional output as soon as December 2026. Cumulatively, Meta is pursuing up to 6.6 GW of nuclear capacity via its Vistra, TerraPower, and Oklo agreements. Both Constellation Energy and Vistra sit on top-quartile forward earnings multiples — Vistra trades at a 13.3x forward P/E despite a 78% one-year share-price run; Constellation Energy trades at ~20.7x forward P/E off $31.3B in trailing revenue and ~22 GW of nuclear capacity.

Rural co-op gas and hyperscaler nuclear are not substitutes — they serve different reliability and price points. But they do compete for capital allocation and regulatory oxygen. The Smarr loan is the first time federal rural-utility financing has been formally aligned with data-center demand, tilting the playing field toward the rural-gas model for the next wave of capacity additions.

Policy Floor

The Court Just Killed the Federal Coal Lifeline — That's Why Gas Loans Are Back

A week before USDA closed the Smarr loan, a federal appeals court shut down the policy lever the Trump administration had been using to keep aging coal plants alive. On September 11, 2026, the D.C. Circuit Court vacated the Department of Energy's Section 202(c) emergency order keeping Consumers Energy's J.H. Campbell coal plant in West Olive, Michigan running past its retirement date, ruling that long-term resource adequacy risks do not constitute an emergency under the Federal Power Act. The court also rejected a follow-on move to compel grid operator MISO to honor the order.

The ruling didn't just retire a single coal unit — it foreclosed the federal government's most aggressive tool for propping up coal-fired baseload. With the \"coal lifeline\" off the table, the next megawatt of new firm capacity has to come from somewhere else. In Georgia, that \"somewhere else\" is now a federally financed combined-cycle gas plant underwritten by RUS, sitting next to a data center campus being built by Alphabet, and adjacent to a coal plant (Southern Company's Plant Scherer) that the state has already ordered kept online to serve the same load.

The Smarr loan is a direct consequence of the J.H. Campbell ruling. Strip the federal Section 202(c) tool away and rural utilities have to fund new firm capacity themselves — and the cheapest, fastest way to do that is a gas plant with a Treasury-rate RUS loan. That dynamic is what Under Secretary Glen Smith meant when he flagged $8.6 billion in pending RUS loan requests only one month into the fiscal year.

Fundamentals Check

Where the Money Has Already Moved — And Where It Hasn't

Three of the publicly traded counterparties in this story already have AI-power exposure priced into their multiples; the fourth — the regulated utility incumbent — does not.

Forward earnings, backlog, and AI-power exposure for the tradeable names
TickerForward P/ELatest revenueKey AI-power metricSource
GEV38.8x$41.4B TTM$176B backlog; >$5B H1 data-center ordersGEV Q2 2026 release
PWR33.0x$32.9B TTM~$44–50B backlog; ~30% of 2026–30 grid-services TAMPWR Q1 2026, Investor Day
VST13.3x$19.2B TTM~2,600 MW Meta nuclear PPA (20-yr); 38.7 GW genVistra 8-K Jan 9, 2026
CEG20.7x$31.3B TTM~22 GW nuclear; Meta/Google/Microsoft PPAsCEG Q2 2026 release
SO~17x (NTM)~$26B (FY2025)Georgia Power IRP: 9,885 MW new gen through 2031Georgia Power 2025 IRP approval, Jul 2025

GE Vernova and Quanta Services have rerated most aggressively: GEV ran a ~28.8x trailing P/E on Q2 TTM revenue of $41.4B and a $176B backlog, and PWR traded at a 73x trailing P/E with a ~$44–50B backlog and 41% year-on-year Q2 revenue growth. Vistra is the cheapest on forward earnings despite locking in 20-year hyperscale PPAs; Constellation Energy sits in the middle with a 20.7x forward multiple. Southern Company, which owns Georgia Power, has a regulated-utility valuation profile and a market cap that has not yet caught up to the data-center load it has been ordered to serve — its investment case is volume-driven rate-base growth, not a multiple rerating.

Horizons

Short-Term Catalysts vs. the Long-Term Buildout

  • Days–quarters (0–9 months): Watch for the next $1B+ RUS loan close. Glen Smith has already telegraphed $8.6B in queued applications; precedent says the next announcements will name other co-ops with combined-cycle or load-serving projects in data-center states (Texas, Virginia, Ohio, Arizona). Also watch for Georgia Power's 2026 all-source RFP awards — those are the contracts that turn this story into EPC backlog for Quanta Services and turbine orders for GE Vernova.
  • 1–3 years (2027–2029): The Smarr plant starts producing revenue into the regional grid by 2029, just as Vistra's Meta uprates begin delivering incremental nuclear output (Perry from Dec 2026, Davis-Besse from Dec 2027). The relative cost of rural co-op gas versus hyperscaler nuclear becomes the most-watched spread in US power; if hyperscaler PPAs reset at higher prices, the value of Constellation Energy's existing book repricing accelerates.
  • Structural risk: The White House's March 2026 \"Ratepayer Protection Pledge\" requires data-center operators to pay for grid upgrades specific to their load — if a hyperscaler pulls back on a county (Google's Monroe rezoning died once in 2025 before reviving in September 2026), the load that justifies rural utility capex goes with it. Southern Company is the most exposed on this axis because its 2025 IRP assumes Georgia data-center load materializes.
  • Policy tail: A second Section 202(c) appeal, or a Supreme Court grant, would reopen the federal coal \"lifeline\" question and undercut the gas-loan thesis. Track the Michigan v. DOE docket and any DOE emergency-action petitions filed in MISO, PJM, or SERC for early signals.

Investable Names Tied to the Rural-Utility / AI-Buildout Thesis

GGE VernovaGEV--
--Vol --
-
Bullish
  • Direct beneficiary: Smarr CC uses two GE Vernova 7HA.03 turbines, same frame that booked >$5B of H1 2026 data-center orders against a $176B backlog
  • Q2 2026 revenue of $11.1B and raised 2026 guide to $45.5–46.5B imply revenue acceleration into 2029 Smarr commercial operation
  • Risk: $176B backlog is already booked; the marginal Smarr-style order is incremental, not a multiple-expander
PQuanta ServicesPWR--
--Vol --
-
Bullish
  • Owns the 500-kV transmission and substation buildout every RUS generation project requires; ~30% of 2026–2030 grid-services TAM
  • ~$44–50B backlog and 41% YoY Q2 revenue growth underwrite visible double-digit growth through 2028
  • Watch: 73x trailing P/E leaves little room for execution misses; Smarr's 7.8-mile, 500-kV interconnect scope is still to be awarded
VVistraVST--
--Vol --
-
Bullish
  • Cheapest AI-power trade on forward earnings (13.3x) with 2,600 MW locked in under 20-year Meta PPAs plus uprates starting Dec 2026
  • Counterweight to the gas thesis: every rural RUS loan that closes is capacity that doesn't have to come from nuclear
  • Risk: commodity-exposed merchant portfolio (coal, gas) gives the multiple its discount; AI exposure is the rerating trigger
CConstellation EnergyCEG--
--Vol --
-
Bullish
  • Three Mile Island restart (835 MW) for Microsoft by 2028 + Clinton (Meta) + Google 890 MW across 11 reactors — biggest contracted AI-power book
  • 20.7x forward P/E leaves room for a single-digit multiple expansion if any PPA is renegotiated upward
  • Risk: state-level opposition to data-center ratepayer cross-subsidies in Illinois could force PPA concessions
MMicrosoftMSFT--
--Vol --
-
Mixed
  • Both a buyer (Three Mile Island PPA, Fairwater Atlanta) and a customer of rural co-op power — Microsoft told the Georgia PSC in 2024 it believed Georgia may be overestimating data-center load growth
  • Fairwater Atlanta (Fayette County) is online; further Atlanta-region growth depends on whether Smarr-style capacity comes online in time
  • Long-term: AI capex is the dominant P&L driver; power-supply reliability is now a gating constraint on capex deployment
GAlphabetGOOGL--
--Vol --
-
Bullish
  • Largest explicit footprint in Monroe County: 948 acres bought Oct 2025 ($42–58M); county approved $1.2B revenue split in Sep 2026
  • Co-located with Smarr CC, Plant Scherer, and the regional transmission upgrades the USDA loan finances
  • Risk: Monroe County already killed one rezoning in Aug 2025; permitting timelines, not power supply, are the binding constraint
MMeta PlatformsMETA--
--Vol --
-
Bullish
  • Pursuing up to 6.6 GW of nuclear (Vistra, Oklo, TerraPower) — the largest contracted AI-power demand on the market
  • Atlanta-region buildout remains a secondary priority behind PJM and Ohio Prometheus data center
  • Hedge: 20-year PPAs lock in price; if hyperscale power costs fall, Meta captures the spread but also bears the volume risk
SSouthern CompanySO--
--Vol --
-
Watch
  • Owns Georgia Power, which is the regulated counterparty for both Alphabet's Monroe load and Microsoft Fairwater; 2025 IRP commits to ~9,885 MW of new generation through 2031
  • Regulated-utility multiple (no AI rerating) but rate-base growth is the cleanest play if data-center load materializes in Georgia
  • Watch: Georgia PSC's December 2025 vote flagged $50–60B in customer cost risk if data-center forecasts miss — the binary is rate-case outcome, not load