Value of the power and grid frames
$17.2B
Venture Global 8-K, Oct. 15, 2026 — if every purchase order is placed
Islands under a definitive reservation
8 of 15
Manufacturing reservation signed with GE Vernova, Oct. 15, 2026
New island capacity
11.52 GW
Up to 16 islands at 720 MW each, deliveries through 2034
GE Vernova gas equipment book
116 GW
53 GW backlog plus 63 GW slot reservations, Q2 2026
Implied fixed liquefaction fee
$6.79/MMBtu
Venture Global Q3 2026 operating update, Oct. 7, 2026
Fuel bill in a $10 gas market
$4.24B/yr
Estimate: 11.52 GW at 60% load, 7 MMBtu/MWh heat rate
Trailing free cash flow
-$9.41B
Twelve months to June 30, 2026, Form 10-Q
On October 9, 2026, Venture Global LNG signed a power frame agreement with GE Vernova Operations and Baker Hughes Energy Services covering up to 16 gas-fired power islands at 720 MW each, plus a grid frame with GE Grid Solutions covering equipment for up to 21 island projects. Venture Global announced it on October 15 as the next step in an off-grid, \"Island-Mode\" power network aimed at data centers, and it turns an LNG exporter into a merchant power marketer for the same molecules it already sells.
The October 9, 2026 agreements
The $17.2 Billion Is a Slot Option, Not a Contract
The headline value is a ceiling, not a price. Neither side is bound to buy or supply an island until definitive reservation agreements and purchase orders are signed; the only committed spend is the reservation fee. Of the fifteen power islands still open under the frame, eight sit under a definitive manufacturing reservation with GE Vernova. The deal locks turbine slots for eight islands and leaves seven to option, and the option expires on a staggered schedule that starts in October 2027.
| Agreement | Scope | Binding today | Next deadline |
|---|---|---|---|
| Power frame: GE Vernova and Baker Hughes | Up to 16 islands at 720 MW, or 11.52 GW, with deliveries through 2034 | A definitive manufacturing reservation with GE Vernova covering eight of the fifteen remaining islands, or 5.76 GW | Purchase order for the first island expected by end-2026; further orders from early 2027 |
| Grid frame: GE Vernova's grid business | Equipment supporting up to 21 power island projects, deliveries through 2034 | Five definitive long-lead reservation agreements for the first five equipment packages | Purchase orders anticipated in late 2026; reservations lapse in stages to mid-December 2026 |
| Combined value | About $17.2 billion if every purchase order is placed, subject to adjustment for reservation fees | No purchase obligation on either side beyond reservation fees and reserved capacity | Unit manufacturing reservations expire in stages from October 2027 to October 2029 |
- GE Vernova now holds a definitive manufacturing reservation covering eight of the fifteen remaining islands, worth 5.76 GW of capacity for deliveries that start in 2028.
- Nothing beyond that is a purchase order. The company describes the agreements as frameworks, with definitive reservation agreements and purchase orders required before any obligation to buy or supply an island arises.
- The grid deadline is the near-term test. Grid capacity reservations lapse in stages until mid-December 2026, weeks before the first turbine purchase order is due at the end of the year.
- Turbine reservations run longer. Unit manufacturing capacity expires in stages from October 2027 to October 2029, which keeps the option alive through the first wave of data center contracts.
- The $17.2 billion is an estimate, not a price tag. Venture Global says the figure is subject to adjustment for reservation fees and other criteria, so it caps the opportunity rather than fixing it.
Why the machines were worth chasing
The Scarce Asset Is a Turbine Slot, Not a Turbine
The turbine is not scarce; the slot is. In the second quarter of 2026 GE Vernova booked 20 GW of new gas equipment while shipping 3 GW — 18 GW of slot reservations plus 2 GW of orders against a quarterly delivery run rate of 3 GW. Venture Global's eight reserved islands equal 5.76 GW, roughly 5% of that 116 GW book and nearly twice everything GE Vernova shipped in the whole quarter.
GE Vernova's gas book is mostly reserved, not sold
GE Vernova Q2 2026 results: gas power equipment backlog rose from 44 GW to 53 GW while slot reservations rose from 56 GW to 63 GW, for 116 GW combined. Management targets at least 125 GW under contract by year-end 2026.
Unit: GW
Firm gas backlog, Q2 2026
53
Slot reservations, Q2 2026
63
New slot reservations signed in Q2
18
Equipment shipped in Q2
3
- The reservation covers 5.76 GW of a 116 GW book, and 11.52 GW if every island converts — close to a tenth of GE Vernova's entire gas pipeline.
- Hyperscalers are in the same auction. Microsoft recently bought seven GE Vernova turbines for a Texas data center, and xAI's Colossus 1 site is already running GE Vernova hardware.
- Price check: spreading the $17.2 billion across 11.52 GW gives roughly $1.5 million per MW of combined turbine-and-grid scope, so the option is not obviously overpriced. The value sits in the slot, not the machine.
- The split between the two suppliers is not disclosed. The definitive manufacturing reservation sits with GE Vernova; how the remaining seven islands split between it and Baker Hughes has not been said.
How the money is made
Two Margin Engines on the Same Molecule
The export business and the power business earn money in different currencies. Venture Global quantifies the export side: a $1.00 per MMBtu change in fixed liquefaction fees moves full-year 2026 adjusted EBITDA by $180 million to $210 million. Island-mode power earns a spread over fuel, and at 11.52 GW running at 60% load a $1.00 per MMBtu move in Henry Hub is worth about $424 million a year of fuel cost. A dollar of gas moves the new book about twice as hard as a dollar of export fee.
| Metric | LNG export book | Island-mode power book |
|---|---|---|
| What is sold | A fixed liquefaction fee on molecules | Firm power to data centers, priced later |
| Disclosed economics | $5.05/MMBtu fee on 91% of 2026 available cargos; $6.79/MMBtu implied fee realized in Q3 2026 | No customer price, contract or project return has been disclosed |
| Sensitivity | $1.00/MMBtu of fee equals $180-210 million of 2026 adjusted EBITDA | $1.00/MMBtu of gas equals about $424 million of fuel cost at full build |
| Gas price direction | Gas passes through on indexed cargoes; basis and volumes are the exposure | Gas is a pure cost; $10/MMBtu implies $70/MWh of fuel |
One dollar per MMBtu: export fee sensitivity against power fuel cost
Export fee sensitivity is the company's own guidance: plus or minus $1.00/MMBtu of fixed liquefaction fee equals $180-210 million of 2026 adjusted EBITDA. The power figure is an estimate: 11.52 GW x 8,760 hours x 60% load x 7 MMBtu/MWh = 423.8 million MMBtu a year.
Unit: US$ millions of annual EBITDA per $1/MMBtu
Export fee move, whole company
195
Power fuel move at full build
424
That is where a $10/MMBtu stress test bites. The EIA projects Henry Hub at $3.48/MMBtu in 2026 and $3.16/MMBtu in 2027, so moving from the 2026 average to $10 adds roughly $2.76 billion a year of fuel cost at 60% load — about 31% of the company's entire $8.7 billion to $9.1 billion adjusted EBITDA guidance. At full load the fuel bill reaches $7.1 billion a year. The power book turns a gas-price-neutral fee earner into a gas-price-exposed spread business.
The fuel and the permits
The Molecules Are Not Yet Secured
The fuel contract behind 11.5 GW does not exist yet. At a 7 MMBtu per MWh heat rate, 16 islands running flat out would burn about 1.9 Bcf/d of gas; at 60% load, roughly 1.1 Bcf/d. The only gas supply agreement on the public record — a Venture Global Plaquemines LNG contract with Citadel Energy Marketing filed with the Department of Energy in March 2026 — covers 36.5 million MMBtu a year, or about 100,000 MMBtu a day. That single filing covers roughly 5% of what the new islands would burn at full load.
- No take-or-pay: the Citadel contract has no take-or-pay provisions and, per the filing, no corporate affiliation with Venture Global — arm's-length supply that does not lock in fuel for a decade-long power asset.
- The grid scope is bigger than the turbine scope: GE Grid Solutions is reserved for equipment supporting up to 21 power island projects against 16 islands in the turbine frame. Either the internal plan exceeds the contracted 16, or the grid scope covers part of the six island-mode plants already operating or under construction.
- Permits, not the Public Service Commission, are the gating item: because the plants sit off the public grid, the company says it does not need Louisiana Public Service Commission approval to build or sell power, but does need other federal, state and parish permits. First applications were expected in the week of October 15.
- Downstream, the molecules stay with their contracted buyers. The company says third-party data center development is separate from and complementary to LNG operations and does not affect existing LNG sales commitments — including the 1.0 MTPA, 20-year deal ConocoPhillips signed on October 1 for 2030 deliveries and the 1.0 MTPA, 20-year deal with Mitsui that starts in 2029.
| Henry Hub | Fuel cost per MWh | Annual fuel cost | Versus EIA's 2026 average |
|---|---|---|---|
| $3.16/MMBtu | $22/MWh | $1.34B | -$0.14B |
| $3.48/MMBtu (EIA 2026 average) | $24/MWh | $1.47B | Base case |
| $5.00/MMBtu | $35/MWh | $2.12B | +$0.65B |
| $10.00/MMBtu (stress case) | $70/MWh | $4.24B | +$2.76B, about 31% of 2026 EBITDA guidance |
Who captures the value
The Turbine Makers Get Paid First, the Customers Last
The chain has four links and only one of them is a turbine sale. GE Vernova and Baker Hughes supply the machines and the long-lead grid gear, the data center developers are the end customers, and Venture Global sits in the middle converting molecules into megawatts with its own gas, its own land and its own balance sheet.
- Upstream, GE Vernova collects on both sides of the deal: turbine islands plus grid packages for up to 21 projects. Electrification orders rose 66% organically to $6.3 billion in the second quarter, with 2026 Electrification revenue guided to $14.5-15.0 billion including about $3.1 billion from Prolec GE, the transformer business behind the grid frame.
- Upstream, Baker Hughes supplies gas turbines, steam turbines, controls and the electrical house for each island plus services through 2034. Power Systems booked $2.6 billion of orders in the second quarter including 2.7 GW of generation capacity, and management now expects more than $45 billion of Industrial & Energy Technology orders across its two-year horizon.
- Downstream, the demand is real but unpriced. Louisiana reporting puts the 10 GW compute ambition roughly 25% above what Meta Platforms's Hyperion campus in Richland Parish will need once fully built out, yet no customer contract price, counterparty or project return has been disclosed.
- Cross-industry, the auction is crowded. Utilities and hyperscalers are competing for the same slot book, and a 720 MW island is a meaningful increment for any single data center campus.
The funding constraint
A Balance Sheet That Cannot Fund the Build
Venture Global cannot fund $17.2 billion of equipment from its own balance sheet, and the non-binding structure of the frame says so. Net debt was $39.62 billion at June 30, 2026 against $3.19 billion of cash and $12.08 billion of total equity, and free cash flow was negative $9.41 billion in the trailing twelve months — after negative $6.80 billion in 2025 and negative $11.57 billion in 2024. Funding the power build requires project-level capital and partners, not export cash flow.
| Line | Amount | Period |
|---|---|---|
| Total assets | $61.52B | As of June 30, 2026 |
| Total debt | $42.81B | As of June 30, 2026 |
| Net debt | $39.62B | As of June 30, 2026 |
| Cash and equivalents | $3.19B | As of June 30, 2026 |
| Total equity, including minority interest | $12.08B | As of June 30, 2026 |
| Operating cash flow | $7.59B | Twelve months to June 30, 2026 |
| Capital expenditure | $17.00B | Twelve months to June 30, 2026 |
| Free cash flow, operating cash flow less capex | -$9.41B | Twelve months to June 30, 2026 |
| Potential equipment spend under the frames | About $17.2B | If every purchase order is placed, 2028-2034 deliveries |
- GE Vernova can self-fund the order: 2026 free cash flow guidance of $11.5 billion to $12.5 billion, raised from $6.5 billion to $7.5 billion, with Power segment EBITDA margin guided at 17% to 19%.
- Baker Hughes enters with a record order book: $10.5 billion of quarterly orders, $7.1 billion of IET orders and $40.1 billion of remaining performance obligations.
- The LNG build is not finished either: Plaquemines Phase 1 is targeted for a fourth-quarter 2026 start-up, Phase 2 for mid-2027, and the Plaquemines Expansion is targeted for a final investment decision in the first half of 2027 with first LNG in 2029 — another capex wave behind the power plan.
Catalysts and risks
What Moves First, and What Matters for Three Years
- October 28, 2026: GE Vernova reports third-quarter results. Watch whether the 116 GW gas book keeps filling with reservations like Venture Global's and whether the 125 GW year-end target survives.
- Mid-December 2026: the first real deadline. Grid capacity reservations lapse in stages until then unless converted into purchase orders, and the company expects the first island purchase order by the end of 2026.
- November 10, 2026: Venture Global's third-quarter results and call — the first chance to see the third-quarter operating data (124 cargos, 465.8 TBtu sold, a $6.79 per MMBtu implied fee) discussed alongside any power pricing.
- The short-term trade is not the export book: 91% of 2026 available cargos are already contracted at a $5.05 per MMBtu fee, and the unsold balance is assumed at $12.50-13.50 per MMBtu.
- 2028 to 2034: deliveries. Island one lands in 2028 and the last of the 16 by 2034, with the compute build-out targeting up to 10 GW by the end of 2034.
- The main risk to the power thesis is the absence of a disclosed customer. Without a data center contract, a price and a partner, the islands cannot be ordered out of a funding-constrained balance sheet.
- The second risk is gas. A $10 per MMBtu Henry Hub adds about $2.76 billion a year of fuel cost at 60% load, roughly 31% of 2026 adjusted EBITDA guidance, and the power book has no contracted pass-through yet.
- The third risk is schedule slippage. Island delivery dates stretch to 2034, so the cash outlay, the customer contracts and the fuel supply all have to arrive in the same decade.
The synthesis
The Valuation Anchor Moves From Cargoes to Power Spreads
The trade is not about LNG export volumes, and it is not really about turbines. Venture Global bought the right to convert 11.52 GW of molecules into firm, off-grid power, and the price of that right — reservation fees rather than plant capital — is small next to the value of the slot it locks. What it did not buy is a customer. Every number that matters from here is a power number: the price of a data center contract, the heat rate of the fleet, and the fuel underneath it. The valuation anchor moves from export cargoes to power spreads.
Investable takeaways
- Reserves 5.76 GW of a 116 GW gas book for Venture Global, with purchase orders expected from early 2027.
- Grid frame covers up to 21 island projects, five more than the 16 turbines, extending Electrification beyond the machines.
- Near term: results on October 28; medium term: 2026 free cash flow guidance of $11.5-12.5 billion funds the capacity.
- Risk: 63 GW of the gas book is slot reservations, so conversion to firm orders proves the thesis.
- Supplies turbines, steam turbines, controls and electrical houses plus services through 2034, a multi-year equipment annuity.
- Power Systems booked $2.6 billion of orders in Q2 2026 including 2.7 GW, with two-year IET orders now seen above $45 billion.
- Near term: the first Venture Global island order by end-2026 sets the pace; deliveries run 2028-2034.
- Caveat: no definitive reservation for Baker Hughes' share of the 16 islands has been disclosed.
- Reservations buy a claim on 5.76 GW of otherwise unavailable capacity, and the frames carry no purchase obligation.
- But $17.2 billion of potential equipment spend lands on $39.62 billion of net debt and $3.19 billion of cash.
- Gas sensitivity flips: $1 per MMBtu of Henry Hub is worth about $424 million of fuel cost, twice the export fee sensitivity.
- Catalysts: first island purchase order by end-2026 and third-quarter results on November 10, 2026.
- Its 1.0 MTPA, 20-year Venture Global supply deal from 2030 is untouched; data center power does not affect existing LNG commitments.
- Medium-term risk: power absorbs up to 1.9 Bcf/d of gas, leaving swing cargoes as the residual claim on molecules.
- Near term: third-quarter results on November 10 will show how the unsold 2026 cargo book is priced.
- Its 1.0 MTPA, 20-year deal with Venture Global starts in 2029, inside the window when the first islands begin burning gas.
- Contracted volumes are protected; the exposure runs to swing cargo availability, not to contracted supply.
- Catalyst: the first island purchase order by end-2026 and any disclosed power contract pricing.
- Hyperion in Richland Parish is the local benchmark: Venture Global's 10 GW ambition runs roughly 25% above that campus's needs.
- Behind-the-meter firm power from an LNG site would be a new supply route, but no counterparty has been disclosed.
- Watch: first Venture Global island purchase order by end-2026 and Louisiana permit filings.