Vistra reported third-quarter GAAP net income of $1,140 million on revenue of $6,347 million, with Ongoing Operations Adjusted EBITDA of $2,378 million — more than 50% above the $1,581 million booked a year earlier. The reconciliation in the company's own Form 8-K shows where that number came from: add back $356 million of income tax, $254 million of interest and $975 million of depreciation, and Vistra strips $559 million of unrealized hedge gains back out to reach the Adjusted EBITDA the market rewards.
| Bridge | Q3 2026 ($M) |
|---|---|
| GAAP net income attributable to Vistra | 1,140 |
| Income tax expense | 356 |
| Interest expense, net | 254 |
| Depreciation and amortization | 975 |
| Unrealized gain on commodity hedges, removed | (559) |
| Other reconciling items | 212 |
| Adjusted EBITDA | 2,360 |
| Asset Closure segment, excluded from Ongoing Operations | 18 |
| Ongoing Operations Adjusted EBITDA | 2,378 |
Unrealized hedge gain/(loss) by segment, Q3 2026
Where the $559 million came from, in $ millions. Vistra reported these inside GAAP net income; none of it sits in Ongoing Operations Adjusted EBITDA.
Unit: $M
Texas
Gain on fixed-price sales
818
Retail
Gain
65
West
Loss
-31
East
Loss
-293
Read that line the other way and the quarter looks different. $559 million of pretax mark inside $1,140 million of net income is roughly $426 million after the 23.8% tax rate implied by the same filing — about 37% of the bottom line is a price on a forward curve, not a dollar of electricity sold. The nine-month figures tell the same story: $2,474 million of net income, $810 million of unrealized gains added back to reach $4,330 million of operating cash flow.
GAAP net income
$1,140M
Q3 2026, reported Nov. 6, 2026
Unrealized hedge gain
$559M
Inside net income; hedges expected to settle in future years
Ongoing Operations Adjusted EBITDA
$2,378M
Q3 2026, more than 50% above $1,581M a year earlier; the mark is excluded from this measure
Operating cash flow
$4,330M
Nine months ended Sept. 30, 2026
Nine-month unrealized gain
$810M
Added back in the cash flow statement, so it never reached cash
- Retail segment Adjusted EBITDA was $98 million in Q3 2026, up from $37 million a year earlier.
- Total generation was 65.5 TWh in the quarter with 94.8% commercial availability and a 94% nuclear capacity factor.
- 2026 Ongoing Operations Adjusted EBITDA guidance was narrowed to $7.1-7.5 billion, and 2027 guidance was initiated at $7.7-8.5 billion.
- Cogentrix closed on Oct. 30, 2026: roughly 5,500 MW of gas capacity for a net purchase price of about $4.0 billion, or $729 per kilowatt, at a multiple of about 6.8 times 2027 Adjusted EBITDA.
- On a $7.1-7.5 billion EBITDA guide, the $4.3-4.7 billion Adjusted FCFbG guide hands roughly $2.8 billion a year to interest, cash tax and maintenance capital before shareholders see anything.
Why the mark grew
A Hedge Gain Means the Market Is Paying Less for Your Power
An unrealized gain on a fixed-price power sale is a statement about the forward curve, not about demand: a generator is paid above market once the curve drops below its hedge strikes. On the third-quarter call management said ERCOT prices are \"trending lower,\" blaming the conversion of crypto mining into data centers and an audit and permitting pause rather than any change in long-run demand. The $559 million gain and the AI-power story are running in opposite directions — the mark gets bigger precisely as the market's willingness to pay for Texas power goes down.
Hedge book as of Oct. 30, 2026
2026 balance, nuclear, coal and renewables
46 TWh, 100% hedged
Expected generation
2027 Texas, nuclear, coal and renewables
51 TWh, 87% hedged
Expected generation
2027 East, nuclear, coal and renewables
97 TWh, 92% hedged
Expected generation
2027 total, gas generation
81 TWh, 93% hedged
Texas60 TWh at 88%; West 4 TWh at 97%
All2027 expected volumes
98% hedged
As of Oct. 30, 2026
All 2028 expected volumes
78% hedged
As of Oct. 30, 2026
- The 2026 guidance bridge removes $1,956 million of unrealized hedge gains, and the 2027 bridge removes $476 million — so the earnings guide is clean even though the net income underneath it is not.
- Management framed ERCOT's price weakness as transitional, tied to crypto-to-data-center conversion and a permitting audit, and said it does not see it as a long-term impact.
- Texas contributed an $818 million unrealized gain while the East segment posted a $293 million unrealized loss, so the curve move was regional rather than a single national verdict.
- Because 98% of 2027 and 78% of 2028 volumes are already sold forward, every dollar of AI-driven price upside is now a volume and contracting question rather than a pricing question.
Transmission
The AI-Power Cash Sits in Contracts, Backlogs and Cargoes
| Link in the chain | Who is on the other side | Hard number | When it settles |
|---|---|---|---|
| Contracted nuclear capacity | Constellation with Alphabet and Microsoft; Talen with Amazon; Vistra with Meta | 20-year agreement covering 890 MW of upgraded nuclear capacity and more than $4.3 billion of plant investment; a 1,920 MW agreement running to 2042 | Cash, in the contracted term |
| Generation equipment | GE Vernova, Baker Hughes, Doosan Enerbility | $197 billion of backlog with gas equipment and slot reservations at 122 GW; $46.4 billion of remaining performance obligations; 12 contracted U.S. gas turbines | On delivery, mostly 2028-2030 |
| Fuel molecules | Cheniere | $1.9 billion of quarterly Adjusted EBITDA with2026 guidance raised to $8.75-9.25 billion; an agreement of up to 4 mtpa beginning in the early 2030s | Over decades |
| Merchant generation | Vistra, Talen, NRG | $559 million of Vistra's net income was an unrealized mark, while Talen reported $138 million of net income on $669 million of Adjusted EBITDA | Whenever the curve moves |
The timing gap is the whole point. Doosan Enerbility shipped its first U.S. gas turbine in October 2026, yet the seven-unit order agreed in March starts delivering one machine a month from May 2029. Vistra's Cogentrix free cash flow accretion moves from high single digits near term to low double digits on average across 2029-2030. Those deliveries land in the same window in which the hedges behind the $559 million gain mature — which is exactly when load that is not yet contracted starts to show up.
- Upstream: GE Vernova grew gas equipment backlog and slot reservations from 116 GW to 122 GW in the quarter and now expects at least 130 GW by year-end 2026, on revenue of $12.6 billion that rose 27% and 2026 revenue guidance raised to $46.5-47.5 billion.
- Upstream: Baker Hughes took $10.8 billion of orders including $5.9 billion of Industrial and Energy Technology orders, with full-year orders guidance raised to $21.5-23.5 billion.
- Upstream: Doosan Enerbility took seven of the 18 large H-class gas turbine orders placed in the United States, more than any competitor, and shipped its first U.S. unit in October.
- Downstream: Amazon, Alphabet and Meta are the offtakers — Amazon holds Talen's 1,920 MW, Alphabet contracted with Constellation in October, and Meta signed a 20-year agreement at Vistra's Perry plant.
- Fuel: Cheniere exported 684 TBtu across 188 cargoes in the quarter and raised 2026 distributable cash flow guidance to $6.05-6.55 billion.
- Because the equipment and molecule layers are paid on delivery and on cargo, they capture AI buildout without carrying a mark-to-market on the power price — the distinction the generator income statement obscures.
Macro and policy
A $325 Cap, a 6,831 MW Gap, and a 4.87% Long End
PJM's 2028/2029 Base Residual Auction cleared at the FERC-approved cap of $325 per MW-day — 2.5% below the prior year's $333.44 — on 138,318 MW of cleared capacity, and it still came up 6,831 MW short of the reliability requirement with a reserve margin of just 14.7%. Only 525 MW of new generation and uprates cleared. The price of reliability is capped and the gap still exists, so the cost of closing it falls on transmission, on load, or on a regulatory cost allocation rather than on a merchant's power curve.
- Capacity cleared at the cap was worth $16.4 billion, and hedged load sits outside the auction price entirely.
- The cleared supply mix was 46% natural gas, 20% nuclear, 18% coal and 5% demand response — the incumbents are paid the capped price while the shortfall goes unresolved.
- PJM's peak forecast for 2028/2029 sits about 2,000 MW above the 2027/2028 forecast, driven by large data center loads entering the reliability requirement.
- The 10-year Treasury yield closed at 4.867% on Nov. 6, 2026, with the intraday range running from 4.81% to 4.91%.
- Vistra's interest expense of $254 million in the quarter annualizes to roughly $1 billion, against net debt of $19.5 billion at June 30, 2026 and roughly $4.0 billion paid for Cogentrix on Oct. 30; the post-close capital structure was not disclosed.
- ERCOT set a record hourly peak of 91 GW on July 22, 2026 and forecasts approximately 367,790 MW of regional demand by 2032.
- At a capped $325 per MW-day and a 4.87% long end, new gas must clear a rate-case hurdle that an already-built plant does not face — which is the real reason Vistra paid about $729 per kilowatt for existing Cogentrix megawatts rather than building them.
A moratorium on data centers in Texas would be \"problematic\" for customers beyond just Vistra. Management called the idea \"a bridge too far\" and said it had not heard the governor-elect or the legislature aligned with it.
The governor-elect disagrees. Gina Hinojosa won the Texas governor's race on Nov. 3, 2026 and has pledged a data center moratorium until new laws are established — the first serious attempt to legislate directly against AI load in the biggest data center market in America. Vistra's own answer is telling: management called the ERCOT interconnection queue \"overstated\" and pushed for higher collateral, take-or-pay commitments and an identified end-user before any request is approved. A backlog of 233 gigawatts of large-load requests is an option, not a contract, and the company's own disclosure now treats it that way.
Next two quarters
Three Dates Decide the Thesis Before Year-End
- Nov. 9, 2026: Constellation and NRG both report third-quarter results. One earns from 20-year contracts and the other from merchant exposure, so the gap between the two prints is the cleanest available read on whether AI load is arriving as cash or as mark.
- Mid-December 2026: the Texas audit of interconnection requests completes and management expects the permit hold to lift around that point, which determines whether the Batch Zero queue is a pipeline or a queue.
- Every quarter through year-end: 2028 volumes are already 78% hedged, so the unhedged AI-power option is being priced now rather than later, and each mark-to-market swing has a smaller offsetting book to absorb it.
- July 2027: PJM's 2029/2030 Base Residual Auction, the first test of whether the 6,831 MW reliability gap gets built or allocated to load.
- Over the next two quarters nothing changes Vistra's 2027 economics, because 98% of those volumes are already sold forward; the argument is about 2029 and 2030.
One to three years
2029 Is Where the Money Lands, and Where the Risks Compound
- Cogentrix contributes roughly 5,500 MW bought at about $729 per kilowatt and 6.8 times 2027 EBITDA; free cash flow accretion turns from high single digits near term to low double digits on average across 2029-2030.
- Vistra's nuclear fleet ran a 94% capacity factor in Q3 2026, so incremental output has to come from uprates and new build — and PJM nuclear uprates are not expected to contribute until 2031.
- Doosan Enerbility delivers its seven-unit U.S. order one machine a month from May 2029, while GE Vernova expects at least 130 GW of gas equipment backlog and slot reservations by year-end 2026.
- Management says it is in active discussions with large-load customers in ERCOT and PJM and sees contracting pathways across a roughly 50,000 MW fleet, but none of that is signed yet.
- The risks compound in the same window: a Texas moratorium, a capacity price pinned at the cap, a forward curve that keeps falling, and a 4.87% cost of capital on the debt that bought the megawatts.
- Because Cogentrix's accretion turns double-digit in 2029 and Doosan Enerbility revenue arrives from2029, the suppliers and the acquirer are paid in the same decade the hedges mature — which is when the market finally finds out what the power is worth.
So who genuinely monetizes AI power? Not the generator whose forward curve does the work, and not the one whose income statement is a mark. The cash is in the twenty-year contracts that already price the megawatt, the order books that get paid on delivery, and the molecules that get shipped on schedule. Vistra's third quarter was a good quarter by every measure the company reports, and the most revealing number in it revealed that the market now pays less for Texas power than it did a quarter earlier.
Where the AI-power economics actually accrue
- Adjusted EBITDA of $2,378 million excludes the $559 million hedge gain, so roughly 37% of reported net income is mark that will not repeat at this scale in 2027.
- 98% of 2027 volumes are already hedged, concentrating any AI-load upside in 2029-2030, when Cogentrix free cash flow turns double-digit.
- Texas policy is now the dominant variable: the governor-elect's data center moratorium pledge lands before the mid-December interconnection audit.
- Over the next two quarters nothing changes Vistra's 2027 economics because those volumes are sold forward.
- A 20-year Alphabet agreement covering 890 MW of upgraded nuclear capacity turns AI demand into contracted cash with no mark-to-market to argue about.
- 2026 Adjusted Operating Earnings guidance of $11.50-12.50 per share rests on contracted volume, the opposite of a merchant hedge gain.
- Third-quarter results due Nov. 9, 2026 are the first clean comparison of contracted nuclear against merchant hedging.
- Over one to three years contracted nuclear cash carries a premium at a 4.87% long end because it needs no rate-case relief to be paid.
- Third-quarter Adjusted EBITDA of $669 million and Adjusted Free Cash Flow of $433 million came with a $1.5 billion accelerated buyback, not a hedge gain.
- 2027 Adjusted EBITDA guidance of $2,500-2,850 million implies about 26% growth at the midpoint, on an Amazon contract running to 2042.
- The 1,920 MW Amazon agreement is the template the AI-power market is now paying for, and it needs no new capacity auction to work.
- Over the next year the capped $325 per MW-day still pays Talen's capacity revenue even as the reliability gap forces new build elsewhere.
- A $197 billion backlog, up $20 billion sequentially, with gas equipment backlog and slot reservations at 122 GW, is paid on delivery rather than on the power curve.
- Third-quarter revenue of $12.6 billion grew 27% and 2026 revenue guidance was raised to $46.5-47.5 billion with free cash flow of $16-17 billion.
- Management expects at least 130 GW of gas slots by year-end 2026, so the scarcity sits in the machine rather than in the megawatt.
- Over one to three years GE Vernova is paid whether or not Vistra's hedge gain ever settles.
- Third-quarter consolidated Adjusted EBITDA of $1.9 billion and a raise of 2026 guidance to $8.75-9.25 billion come from cargoes already contracted, not from a curve.
- 684 TBtu were exported across 188 cargoes in the quarter, and an agreement of up to 4 mtpa begins in the early 2030s.
- Distributable cash flow guidance rose to $6.05-6.55 billion for 2026, adding a decade of contracted duration to the book.
- Over one to three years contracted molecules are the cleanest AI-power proxy because every cargo is priced before it sails.
- Orders of $10.8 billion including $5.9 billion of Industrial and Energy Technology orders and a record $46.4 billion of remaining performance obligations extend the LNG and power-equipment cycle.
- Full-year Industrial and Energy Technology order guidance was raised to $21.5-23.5 billion.
- GAAP net income fell 33% to $411 million even as backlog set a record, so the order book is not yet reaching the bottom line.
- Over one to three years cash conversion lags the backlog by years, the same lag that flatters generator earnings today.
- Doosan won seven of the 18 large H-class gas turbine orders placed in the United States and shipped its first U.S. turbine in October 2026.
- The company targets an order backlog of about 48 trillion won by 2030 as data center-driven gas power demand grows 3.2 times.
- Deliveries on the seven-unit March order start one machine a month from May 2029, so revenue lags the order by roughly three years.
- Over one to three years the Korean challenger converts American data center demand into Korean backlog long before it converts into earnings.
- Second-quarter Adjusted EBITDA of $1,217 million and Adjusted EPS of $1.49 show a merchant platform that is still earning on realized spreads.
- ERCOT prices trending lower, as Vistra's management described, cuts directly into unhedged merchant margin in the second-largest data center market in the country.
- Third-quarter results are due Nov. 9, 2026, the cleanest merchant read available alongside Constellation.
- Over the next year the Texas policy outcome matters more to NRG than the forward curve does, because it determines whether the load ever arrives.