Alliant Energy Wants 1 GW of Data-Center Contracts in Six Months — but the Bottleneck Is a Rate Docket, Not a Turbine insight cover
Markets / EventLNT · GEV · VRT•25 min read

Alliant Energy Wants 1 GW of Data-Center Contracts in Six Months — but the Bottleneck Is a Rate Docket, Not a Turbine

Alliant Energy's chief financial officer said on October 30, 2026 that the company expects to sign roughly one additional gigawatt of contracted data-center load within six months, on top of the 3.4 GW already under contract with Alphabet, Meta and QTS. That headline is a capital decision dressed as a sales win: at the CFO's own $2–3 billion of capital per gigawatt, one more gigawatt is about 13% of a five-year program now worth $18.8 billion and requires roughly $800 million to $1.2 billion of new equity. The revenue clock does not start at the signature — Alliant's own process runs from electric service agreement to individual customer rate approval to construction, and management expects the Wisconsin decisions that unlock the new load in the first half of 2027. The equipment chain is paid at order and delivery in 2028–2029 while the utility waits for rate cases that push earnings into 2030 and beyond, which is why the AI load trade is cleaner expressed through the supply chain than through the utility's balance sheet.

Published Oct 30, 2026Updated Oct 30, 2026

Additional data-center load targeted

~1 GW

Within six months of the Oct. 30, 2026 earnings call, on top of 3.4 GW already contracted

2027–2030 capital plan

$15.9B

Raised 19% with third-quarter 2026 results on Oct. 29, 2026

Capital cost of one more gigawatt

$2–3B

CFO rule of thumb for incremental capital expenditure

Rate base growth vs. earnings target

13% vs. 8%+

Gap attributed mostly to equity issuance, Oct. 30, 2026

Additional data-center load targeted

~1 GW

Within six months of the Oct. 30, 2026 earnings call, on top of 3.4 GW already contracted

2027–2030 capital plan

$15.9B

Raised 19% with third-quarter 2026 results on Oct. 29, 2026

Capital cost of one more gigawatt

$2–3B

CFO rule of thumb for incremental capital expenditure

Rate base growth vs. earnings target

13% vs. 8%+

Gap attributed mostly to equity issuance, Oct. 30, 2026

Federal loan package

$5.1B

30-year loans closed in October 2026, supporting more than 2,600 MW

Next regulatory decisions

H1 2027

Wisconsin large load tariff and the second Cedar Rapids customer rate

THE OCTOBER 29 EARNINGS RELEASE

The Sprint Is a Capital Promise Wearing a Sales Costume

On October 29, 2026, Alliant Energy reported third-quarter GAAP earnings of $1.52 per share against $1.09 a year earlier, narrowed 2026 ongoing EPS guidance to $3.41–$3.46 from $3.36–$3.46, and guided 2027 to $3.63–$3.73. The number that mattered came from the call the next morning, when CFO Robert Durian said the company expects to produce approximately one additional gigawatt of contracted large load within the next six months. Add the 3.4 GW already contracted with Alphabet, Meta and QTS and the target takes Alliant to 4.4 GW of contracted data-center demand — the biggest book at the smallest utility carrying it. On the CFO's own capital-per-gigawatt math, the announcement commits roughly $2.5 billion of capital before a single rate docket opens.

Capital plan as updated with third-quarter 2026 results; excludes AFUDC and capitalized interest.
$ millions202620272028202920302026–2030
Total capital expenditure2,8604,3054,7354,2852,61018,795
Thermal generation and LNG1,2502,0901,8551,6551,2058,055
Renewables and energy storage6951,2501,8901,6503355,820

Capital expenditure plan, 2026–2030

Updated with third-quarter 2026 results. Generation and storage account for $13.9 billion of the $18.8 billion total.

Unit: $ millions

2026

Up from $2,483 million spent in all of 2025

2,860

2027

First full year of the refreshed four-year plan

4,305

2028

Peak spending year

4,735

2029

4,285

2030

2,610

The reframe matters because the plan, not the contract, is the commitment. Alliant's capital expenditure runs $2,860 million in 2026, $4,305 million in 2027 and $4,735 million in 2028 — a step-up of more than 50% from the $2,483 million it spent in all of 2025. Add the 2026 year to the $15.9 billion four-year plan and the company is committing $18.8 billion, roughly 4.3 times its FY2025 revenue of $4.36 billion. Spends more than four years of revenue on a five-year program, funded with a dividend that grew to $2.14 per share for 2026 and is now targeted at $2.25 for 2027.

At the CFO's own $2–3 billion of capital per gigawatt, one more gigawatt of contracted load is roughly $2.5 billion — about 13% of the $18.8 billion 2026–2030 program and more than the entire 2026 capital budget of $2,860 million. It forces another plan revision, not just another signature.

REGULATORY SEQUENCE

The Approval Queue, Not the Power, Is the Bottleneck

The most useful slide Alliant showed in March 2026 was a four-step chain: customer electric service agreement signed, individual customer rate filed, individual customer rate approved, construction started. Nothing in that chain is about megawatts; it is about a docket calendar. Alliant already has three matters in front of the Wisconsin Public Service Commission — the Cedar Rapids individual customer rate for Alphabet (docket TF-2025-0007) and the QTS 1 Cedar Rapids rate (TF-2025-0047), both approved, and the Beaver Dam individual contract rate for Meta (docket 6680-TE-115), approved in modified form on May 7, 2026. In that same order the commission required Alliant to file a utility-wide tariff for every data center above 100 MW and to serve all future hyperscale sites under standardized terms. A gigawatt now turns into a rate case before it becomes a revenue line.

Regulatory queue as described on the third-quarter 2026 earnings call and in company filings.
ActionStatusTiming
Sign about 1 GW of additional data-center loadManagement targetBy April 2027
Wisconsin large load tariff for customers above 100 MW (docket 6680-TE-119)Application filed Sept. 4, 2026Decision expected H1 2027
Individual customer rate, second Cedar Rapids data-center projectFiledDecision expected H1 2027
Individual customer rate, QTS Clinton data centerTo be filedH1 2027
Wisconsin retail electric and gas base rate review, 2028–2029 test yearsTo be filedSpring 2027
720-MW Bobcat Energy Center, MarshalltownApproved; construction startLate 2026, commercial operation 2029
  • Decisions, not signatures, set the clock: the 2027 guide of $3.63–$3.73 already assumes realization of expected revenues from new data-center demand, so a docket delay lands directly in guidance.
  • The commission's own stated worry is a patchwork of bespoke contracts that leaves costs and responsibilities unclear and potentially shifted onto other utility customers — which is exactly why standardized terms were ordered.
  • Wisconsin's other large utility set the template in April 2026, when the commission approved its very large customer tariff with the eligibility threshold lowered from 500 MW to 100 MW, a minimum initial term extended to 15 years, and the capacity-only option removed so customers carry all generation cost.
  • The general rate case is the last gate, not the first: the spring 2027 filing for 2028 and 2029 test years is where the capital behind this load actually enters rate base, which is why revenue lands in 2030 and beyond even if contracts are signed by April 2027.
A signed electric service agreement is a promise to serve; it is not permission to recover. Until the commission approves the tariff and each individual customer rate that follows, the load is a megawatt figure on a slide rather than revenue in a rate base. Every new contract must clear a rate docket before construction starts.

THE EQUITY MATH

One More Gigawatt Is a $2.5 Billion Decision With a Billion-Dollar Equity Tail

Here is the number that matters more than the gigawatt. Management funds roughly 40% of incremental capital expenditure with common equity — the low end of its stated 40%–50% range — and the refreshed four-year plan carries $2.7 billion of common equity, of which $1.1 billion is already secured through forward agreements that cover expected needs through the first half of 2028. The rest, plus whatever the new gigawatt requires, has to be sold into the market. Management attributes roughly 375 basis points of the growth gap to equity issuance and about 50 basis points to refinancing.

  • Rate base plus construction work in progress is compounding at 13% while the long-term earnings target is 8% or better, and that gap has to be funded rather than explained.
  • Needs roughly $800 million to $1.2 billion of new stock for one gigawatt, close to all of FY2025 net income of $810 million.
  • The $1.0 billion at-the-market program had produced only $59 million of issuance through September 30, 2026 because management prefers forward sales, which are cheaper but price the dilution today.
  • FY2025 free cash flow was negative $1.31 billion — $2,483 million of capital expenditure against $1,169 million of operating cash flow — with the gap closed by $1,700 million of net debt issuance and $521 million of dividends.
  • Caveat: cheaper financing helps shareholders only to the extent that the savings stay in the utility's revenue requirement rather than being passed through in lower bills. Regulators decide that split, and the rate docket is where it gets argued.
The federal loan package closed in October 2026 is the first material offset to that equity math: $5.1 billion of 30-year loans supporting more than 2,600 MW of new or upgraded capacity — roughly 1,500 MW of new gas generation, 240 MW of uprates at existing units and 1,000 MW of battery storage. DOE-backed financing cuts annual interest expense by more than $46 million, with up to $1.2 billion of projected customer savings over the life of the loans.

THE PEER MAP

Who Actually Captures AI Load: Contract Quality Beats Headline Megawatts

Set the megawatt counts side by side and Alliant looks like the winner: 3.4 GW contracted on FY2025 revenue of $4.36 billion, more contracted load per dollar of sales than any peer. Read the contract structures and the picture changes. Evergy's 2026 electric service agreements cover about 2,600 MW and already sit in $16.0 billion of remaining performance obligations across three operating companies, on weighted-average remaining terms of 14 to 17 years. Ameren's Missouri operation signed binding agreements totaling 2.2 GW in February 2026, with customers committing to pay for 80% of their requested electricity for at least 12 years. And the Wisconsin utility of WEC Energy Group won a very large customer tariff in April 2026 with a 15-year minimum initial term and full responsibility for generation costs. On that reading, Alliant Energy has the most megawatts and the least contract certainty.

Contracted load, contract structure and balance-sheet scale. Revenue and EBITDA for fiscal 2025; contracted megawatts per dollar of revenue is calculated from those figures.
Alliant EnergyEvergyAmerenWEC Energy Group
Contracted data-center load3.4 GW, plus about 1 GW targetedAbout 2.6 GW2.2 GW1,300 MW campus announced
Contract structureBespoke agreements; individual customer rates under a tariff still pendingLarge load tariffs; 14–17 year weighted-average remaining terms; $16.0B of contracted obligations80% take-or-pay for at least 12 years, with collateralVery large customer tariff; 15-year minimum term; 100% of generation cost
FY2025 revenue$4.36B$5.92B$8.80B$9.80B
FY2025 EBITDA$2.02B$2.68B$4.04B$4.05B
Contracted MW per $1B of FY2025 revenue780 MW439 MW250 MW133 MW
Funding signalFY2025 free cash flow of negative $1.31B; about 40% of incremental capital funded with equityLarge load tariffs approved in Kansas and MissouriAlmost 10,000 MW of new generation in a 20-year plan15-year minimum term already approved

The disclosure gap is the tell. Evergy publishes contracted obligations and weighted-average remaining terms; Alliant publishes megawatts and a growth rate. Alliant Energy leaves its 3.4 GW book unpriced in public disclosure, which is part of why the equity market rather than the commission is being asked to fund it. The offsetting point is real: Alliant has said all growth in its plan is contractually secured by long-term electric service agreements with high-quality customers, and its 2027 guidance already assumes new data-center revenue. Whether the standardized Wisconsin tariff preserves the economics of those bespoke contracts is exactly what the commission will decide in the first half of 2027.

THE EQUIPMENT QUEUE AND CHEAP CAPITAL

Upstream: The Equipment Queue Sets the Pace and the Price

The upstream shows where the money actually goes. GE Vernova booked 16.6 GW of gas turbine orders in the third quarter of 2026 alone and 36.7 GW over nine months, and its Power segment equipment backlog more than doubled to $54.4 billion from $24.7 billion at the end of 2025; total remaining performance obligations reached $196.7 billion. Alliant's 1.2 GW of additional combustion turbines is roughly 7% of a single quarter's industry orders — immaterial for the utility, decisive for the supplier. The physical queue is tighter still: step-up transformer lead times passed 160 weeks by the first quarter of 2026, against an average of 143 weeks in 2024. The manufacturer is paid at order and delivery while the utility waits for a docket.

  • GE Vernova booked 16.6 GW of gas turbine orders in the third quarter of 2026, and Power equipment backlog of $54.4 billion against $24.7 billion at the end of 2025.
  • Siemens Energy and GE Vernova hold the heavy-duty turbine market, so Alliant's 1.2 GW of new combustion turbines is a queue position rather than a purchase order, with several units of new manufacturing capacity slated for 2027.
  • Alliant's federal package adds about 1,500 MW of new gas generation, 240 MW of uprates and 1,000 MW of batteries — cheap public money substituting for utility equity in the same asset base.
  • Transformer and switchgear lead times, not generation queues, are what push Alliant's first generation dollars into 2026–2029 and its rate base earnings into 2030 and beyond.
Order books, not rate cases, are where the AI power build monetizes first. The turbine and transformer order is placed the same day the contract is signed, and the manufacturer gets paid on delivery in 2028–2029, while the utility waits for a commission decision before it earns on the asset in 2030. That timing gap, not the megawatt count, decides who captures the build.

THE CUSTOMERS WHO HAVE TO BUILD IT

Downstream: Three Customers, Three Clocks

A gigawatt is only a contract if the counterparty builds. Alphabet's capital expenditure reached $51.4 billion in the third quarter of 2026 and $132.0 billion over the first nine months, with negative free cash flow of $9.1 billion in the quarter — a funding capacity that makes Alliant's 1 GW a rounding error on the customer's side. Meta has committed more than $1 billion to the Beaver Dam campus. QTS, the data-center platform owned by Blackstone, is building a Cedar Rapids campus expected to draw about 1.05 GW of electricity. The equipment layer confirms the money is real: Vertiv reported third-quarter net sales of $4.31 billion, up 61% year over year, with organic orders up more than 100%. Vertiv's customers prepaid $4.1 billion for equipment that has not shipped, 3.6 times the level a year earlier.

  • Alphabet has two Cedar Rapids projects: the first individual customer rate is approved, the second was filed with a decision expected in the first half of 2027.
  • Meta has more than $1 billion committed at Beaver Dam, but the commission approved a modified version of the special contract and ordered a standardized tariff for future sites — the terms moved against the customer.
  • Blackstone, through QTS, is building the Cedar Rapids campus expected to draw about 1.05 GW, and Alliant plans to file an individual customer rate for the QTS Clinton project in the first half of 2027.
  • Vertiv booked third-quarter net sales of $4.31 billion with organic orders above 100%, implying roughly $4.4 billion of fourth-quarter shipments against full-year guidance of about $14.65 billion.
The customers are paying the equipment chain in cash today while the utility waits for 2029–2031 rate cases. That asymmetry, not the megawatt count, decides who captures AI load: suppliers collect cash on delivery while the utility waits for a docket.

NEXT SIX MONTHS AND THE NEXT THREE YEARS

Horizons: What to Watch, and When

  • Q4 2026 and Q1 2027 results: watch how much of the $1.0 billion at-the-market program is used and whether the one-gigawatt target is repeated on the February and April calls.
  • The Wisconsin large load tariff decision, expected in the first half of 2027, sets the cost-allocation terms for every Alliant data-center contract above 100 MW — including the gigawatt being sold.
  • Expects both the second Cedar Rapids customer rate and the QTS Clinton filing in the first half of 2027, so the commission's calendar rather than new signings determines the shape of 2027.
  • The Wisconsin base rate review for 2028 and 2029 test years, to be filed in spring 2027, is where the capital behind this load enters rate base.
  • The 2027 guide of $3.63–$3.73 already assumes new data-center revenue, so an approval delay is a guidance event rather than a timing nuisance.
  • Rate base compounding at 13% against an 8% earnings target means the equity question repeats annually: each incremental gigawatt adds roughly 375 basis points of dilution unless cheap capital keeps substituting for stock.
  • The 720-MW Bobcat Energy Center starts construction in late 2026 and targets commercial operation in 2029 — the first hard checkpoint on whether utility-owned generation tracks the data-center ramp.
  • The dividend target rises to $2.25 per share for 2027 from $2.14, slower than the 8% earnings goal, which is how the cash strain is being managed in plain sight.
Three queues sit between the headline and the shareholders: a commission docket, a turbine and transformer order book, and an equity market. The first two are slow but visible; the third never closes. In the AI power build, the approval queue decides who gets paid, and when.

Three things can be separated cleanly. Facts: Alliant has 3.4 GW contracted, a $15.9 billion four-year capital plan, and a $5.1 billion federal loan package that lowers its funding cost. Inference: the six-month gigawatt is a financing decision as much as a commercial one, because the capital has to be committed before the load can be approved for recovery. Speculation: where the additional gigawatt lands, and how generous the standardized tariff turns out to be relative to the bespoke contracts it replaces, are both unresolved until the commission rules in the first half of 2027. The defensible position is narrow — the funding is largely solved and the payoff timing is not.

Where the AI load actually gets paid

LAlliant EnergyLNT--
--Vol --
-
Mixed
  • One more gigawatt implies roughly $2.5 billion of capital at the CFO's own rule of thumb — about 13% of the $18.8 billion 2026–2030 program.
  • Alliant Energy funds 13% rate base growth with equity that dilutes 8% earnings growth, with 375 basis points of the gap attributed to share issuance.
  • Near term: the Wisconsin large load tariff and the second Cedar Rapids customer rate, both expected in the first half of 2027, set the terms for the new load.
  • Longer term: the $5.1 billion federal loan package cuts interest expense by more than $46 million a year, offsetting much of the annual dilution.
GGE VernovaGEV--
--Vol --
-
Bullish
  • Third-quarter gas turbine orders of 16.6 GW and Power equipment backlog of $54.4 billion show utility AI capex converting straight into OEM revenue.
  • GE Vernova monetizes Alliant's 1.2 GW of new combustion turbines without waiting for the Wisconsin rate case that lets the utility earn on them.
  • Near term: the third-quarter order book is already booked; the new signal is the 1.2 GW of turbines inside Alliant's refreshed $8.1 billion thermal program.
  • Longer term: slot reservations are not firm orders, so backlog can convert later than the build schedule assumes.
VVertivVRT--
--Vol --
-
Bullish
  • Third-quarter net sales rose 61% to $4.31 billion with organic orders up more than 100%, tracking the same hyperscaler spending that funds Alliant's contracted load.
  • Vertiv collects cash before the utility earns anything: customers had prepaid $4.1 billion for undelivered equipment as of September 30, 2026.
  • Near term: full-year guidance of about $14.65 billion implies roughly $4.4 billion of fourth-quarter shipments.
  • Longer term: order growth above 100% is the cleanest public read on whether contracted data-center load is actually being built.
AAmerenAEE--
--Vol --
-
Bullish
  • Missouri's 2.2 GW of binding agreements carries an 80% take-or-pay commitment for at least 12 years — firmer than a bespoke contract awaiting a tariff.
  • Ameren converts data-center load into rate base with less regulatory risk than Wisconsin's bespoke-contract model.
  • Near term: almost 10,000 MW of new generation in the 20-year plan keeps the build funded well beyond current contracts.
  • Longer term: FY2025 revenue of $8.80 billion and EBITDA of $4.04 billion give Ameren roughly twice Alliant's capacity to fund the same build.
EEvergyEVRG--
--Vol --
-
Bullish
  • About 2,600 MW of signed agreements already sit in $16.0 billion of remaining performance obligations on 14-to-17-year weighted-average terms.
  • Evergy has already banked the contract economics that Alliant is still seeking regulatory approval to recognize.
  • Near term: service begins between 2026 and 2028, with transitional load periods of up to five years smoothing the ramp.
  • Longer term: Evergy is the benchmark for what a transferable large-load contract book looks like in public disclosure.
GAlphabetGOOG--
--Vol --
-
Mixed
  • Third-quarter capital expenditure of $51.4 billion and $132.0 billion over nine months make Alliant's 1 GW a trivial commitment for the customer.
  • Alphabet waits on Wisconsin rate decisions before it can energize the second Cedar Rapids project, expected in the first half of 2027.
  • Near term: the first Cedar Rapids individual customer rate is approved; the second is filed and awaiting a decision.
  • Longer term: $132.0 billion of nine-month spending gives Alphabet the option to re-site load, which weakens utilities' pricing power.
MMeta PlatformsMETA--
--Vol --
-
Mixed
  • More than $1 billion is committed at Beaver Dam, but the commission approved a modified special contract and ordered a standardized tariff for future sites.
  • Meta faced terms moving against it when its special contract was rewritten — a caution for hyperscalers in other jurisdictions.
  • Near term: Alliant's Wisconsin tariff decision in the first half of 2027 sets the template for Meta's next Alliant-served project.
  • Longer term: standardized tariffs scale quickly but cap bespoke cost allocation for very large campuses.
BBlackstoneBX--
--Vol --
-
Bullish
  • QTS is the contracted counterparty on two of Alliant's three data-center projects, including the Cedar Rapids campus expected to draw about 1.05 GW.
  • Blackstone backs QTS's power position into a standardized tariff once Wisconsin rules on Alliant's large load tariff in the first half of 2027.
  • Near term: an individual customer rate application for the QTS Clinton project is due to be filed in the first half of 2027.
  • Longer term: contracted power supply, not land, is the scarce asset for QTS's development program, and long-dated tariffs make that supply bankable.